We cut cabinetry for the room it goes in, from the drawings we made of that room. Rift oak, fluted bases, unlacquered brass.

Cabinetry is the longest lead item in the second half of a renovation, and it is also the surface you will touch every day for twenty years. That combination is why it decides your finish date more than anything else you choose.

Most firms subcontract it, which means the date belongs to a shop you have no contract with and the site waits in their queue. Ours is in our own building. That matters for one practical reason: a field dimension that has moved gets caught by the people who drew it, before it becomes expensive plywood.

The scope

  1. KitchensFull kitchens including islands, tall units, panelled appliances and the integration with stone and appliances.
  2. Wall units and built-insLibraries, media walls, window seats and the shelving that has to hold something specific.
  3. Vanities and bathroom joinerySized to the plumbing rough-in as it was measured on site.
  4. Closets and dressing roomsFitted to what goes in them.
  5. Panelling, trim and doorsWall panelling, casing profiles and the details that carry a language through a house.
  6. FurnitureDrawn and built alongside the millwork when nothing off the shelf fits the room.
How long

The sequence

Design and millwork drawings
3 to 5 weeks
Field dimensions after framing
1 week
Shop drawings and approval
2 to 3 weeks
Fabrication
10 to 16 weeks from approval
Installation
1 to 3 weeks
Stone template, fabrication and install
2 to 3 weeks after cabinets are set

Stone is the item people do not plan for. It cannot be templated until the cabinets are installed. Then it is fabricated, then installed. That is two to three weeks in the middle of your kitchen with the counters away being made. Other trades can work around it and we plan for that, but the order cannot be changed.

What it costs, and what moves it

Custom cabinetry is typically one of the two largest line items in a whole-home renovation, alongside the mechanical work. It is also the easiest line to test: in a house with walls that are not square, the fit is the whole job and fillers are where stock shows. In a 2015 subdivision build with square rooms and standard ceiling heights, the case is much thinner.

The costs that move a millwork number are the ones people do not price at the start: panelled appliances, integrated lighting, specialty veneers with a matched grain, and any change made after shop drawings are approved. A change after approval can mean material that is already cut.

What to ask, whoever you hire

Take this list to us and to everyone else you are considering. The answers are more useful than the portfolios.

  • Is the shop yours, and can I walk it? What machinery is in it?
  • Are the field dimensions taken before or after the drywall goes on?
  • What happens if an appliance spec changes after shop drawings are approved?
  • What is the lead time from my approval, and what is the penalty if it slips?
  • What is the finish, who applies it, and where is it applied?
  • What is the warranty on doors and drawer fronts, and does it cover seasonal movement?
Built

Projects

Questions we get on this

How long does custom cabinetry take?
Ten to sixteen weeks from approved shop drawings to delivery. The clock starts the day you approve them, so any time spent deciding on a door profile is added to your finish date.
Is custom cabinetry worth it against stock?
Often not. In a newer build with square rooms and standard ceiling heights, a good stock kitchen with two custom pieces around it is usually the better spend, and the money saved is better put into the things that cannot be changed later. Older houses are where custom earns the difference. We build our own millwork, so treat that as an interest declared.
When is the stone templated?
After the cabinets are installed, never before. The dead time it creates is described above. What matters when you are comparing quotes is that a firm promising to compress it is probably planning to template off the drawings, which is how counters arrive that do not fit.